library(tidyverse)
|
|
YEAR <- 2028:2036
|
|
CONSTRUCTION_CAPEX <- c(1860,1860,3720,3720,3720,3720,1860,1860,0)*10^6
|
|
CONSTRUCTION_CAPEX_PER <- CONSTRUCTION_CAPEX/sum(CONSTRUCTION_CAPEX )
|
|
CONSTRUCTION_CAPEX_PER
|
|
1.6/4.8
|
|
32.22461+14.48984+0.41316
|
|
|
|
EMPLOY_COMP_PER_100 <- (22119136.41597/230)*100 #Total payroll from Peabody divided by number of employees
|
|
88*EMPLOY_COMP_PER_100/100
|
|
|
|
POWER_GEN_EQUIP <- CONSTRUCTION_CAPEX_PER*3062082645#*0.8 #80% local spending
|
|
GENERAL_BUILDINGS <- CONSTRUCTION_CAPEX_PER*1871548496
|
|
PLANT_EQUIP <- CONSTRUCTION_CAPEX_PER*5248715967#*0.60 #69% local spending
|
|
OP_UNITS <- c(0,0,0,0,2,2,4,4,6)
|
|
PER_OP <- OP_UNITS/max(OP_UNITS)
|
|
PLANT_WORKERS <- (230-17)*PER_OP +(OP_UNITS>0)*17 # This is an equation of number of power plant operators based on the start date of each generation united provided by Peabody.Regression using Wyomign Impact Statement data shows addtions to existing plants have 17 less workers per MW, implying a minmum of 17 needed. The model was made to assume a start of 17 works with a linear fit thereafter. Peabody provided the 230 final operating worker number.
|
|
#Note average $96,170.16 total payrole (includes benefits) per worker. used in IMPLAN
|
|
|
|
cbind(YEAR,cbind(cbind(POWER_GEN_EQUIP,GENERAL_BUILDINGS,PLANT_EQUIP)/10^6,PLANT_WORKERS))
|
|
#0.228+0.233+0.467+0.472+0.473+0.382+0.248+0.1
|
|
#0.231 +0.237 +0.484 +0.499 +0.515 +0.522 +0.308 +0.300 +0.039 +0.027
|
|
#1-(0.257 +0.264 +0.540 +0.559 +0.578 +0.585 +0.324 +0.313 +0.044)/5.2
|
|
|
|
#Data Center Inputs
|
|
PREDEV_2026 <- 1595000+2392500
|
|
PREDEV_2027 <- 2*2392500+797500
|
|
PREDEV_2026/10^6
|
|
PREDEV_2027/10^6
|
|
|
|
UTILITY_2026 <- 10^6
|
|
UTILITY_2027 <- 21428571+2*32142857
|
|
UTILITY_2028 <- 2*32142857
|
|
round(c(UTILITY_2026,UTILITY_2027 ,UTILITY_2028 ) /10^6 ,2)
|
|
CONS_2026 <- 150000+450000
|
|
CONS_2027 <- 450000+7950000+450000+4287501
|
|
CONS_2028 <- 186328937+216309410+468145389+791934505
|
|
CONS_2028/10^6
|
|
CONS_2029 <- 468145389+247398869
|
|
|
|
CONS_TOTAL <- c(CONS_2026,CONS_2027,CONS_2028,CONS_2029)/10^6
|
|
#Split based on research
|
|
BUILDING <- 0.196
|
|
COMPUTERS <- 0.682
|
|
OTHER <- 0.061
|
|
TOTAL_PER <- BUILDING+COMPUTERS+OTHER
|
|
BUILDING <- BUILDING/TOTAL_PER
|
|
COMPUTERS <- COMPUTERS/TOTAL_PER
|
|
OTHER <- OTHER/TOTAL_PER
|
|
BUILDING+COMPUTERS+OTHER
|
|
##Million Dollar inputs
|
|
CONS_TOTAL*BUILDING
|
|
CONS_TOTAL*COMPUTERS
|
|
CONS_TOTAL*OTHER
|
|
|
|
#Building tax base
|
|
sum(CONS_TOTAL*BUILDING)
|
|
|
|
EMP_2027 <-13.1
|
|
EMP_2028 <- 39.4
|
|
EMP_2029_FORWARD <- 52.5
|
|
|
|
|
|
|
|
|
|
|